Get updates
Preferences
Expand group
PUD Fiber
SkyFi
TV
Purpose:
Upgrade OLT software on the following OLTs
College, Sunnyslope,
Squilchuck, Saddlerock, Wenatchee
DATE:
04/23/2026 - 04/24/2026
Time:
11:00 PM – 04/23/2026 - Start
06:00 AM 4/24/2026 - End
Impact:
15-20 Min outage on each OLT while we upgrade the software.
MASON PUD 3 SERVICE AFFECTING WORK SCHEDULED FOR 4/22/2026
Mason PUD 3 has scheduled service affecting work for 4/22/2026. This work will start at 01:00am and will continue through the day until mid to late afternoon.
This work is service affecting for the roads listed below -
Prairie Lp RD
Fairway Dr
Blakely Dr
W Star Lk Dr
W Lolo Pl
Quinault Trl
W Hoquiam Trl
W Satsop Cloq Rd
W Hamma Hamma Dr
W Dosewallips Tr
W Tulalip Tr
W Chinook Ct
W Tipi Ct
W Cloquallum Rd
W Chimacum Dr
W Arrowhead Dr
W Hoko Pl
W Thunderbird Dr
W Hoh Circle
Kiowa Pl
W Star Pt Way
W Totem Dr
W Tyee Pl
W Bulb Farm Rd
W Lost Lk Rd
W Lost Lk Vw Dr
W Lost Lk Pk Ct
W Frosty Ln S
W Lake Forest Ln W
W Lake Forest Ln E
W Lakeside Dr
W White Rd
Per Grant PUD: The power disruption caused by the pole fire has been resolved and fiber services are operating as expected.
A pole fire in Ephrata has caused an internet service disruption. At this time there is not estimated time to restore service, but we will communicate one as soon as it's available.
Chelan PUD Manson Maintenance Today 4/15/26 8AM-5PM
The total affected customers is 16
NoaNet will be performing maintenance in Davenport that will affect Fiber and Wireless services.
Date of Work: April 14, 2026 - April 14, 2026
Time of Work: 0100-0500 PDT
Est. Outage Duration: Up to 4 Hours
Severity: Service Affecting
CCPUD NETWORKS EMERGENCY MAINTENANCE NOTICE - Repair Rodent Damage - 3/24/2026 3:30 PM - 3/25/2026 1:00 AM - Service Affecting
TITLE: Repair Rodent Damage
LOCATION: Wenatchee
START TIME: 3/24/2026 3:30 PM
END TIME: 3/25/2026 1:00 AM
Services Affected: All Services
Purpose: This outage is required to repair rodent damage on a Fiber cable.
Tuesday, March 24th, LocalTel has scheduled necessary network maintenance from 12:00AM to 6:00AM, in Chelan and Douglas County. This maintenance is being done to make critical updates to our network infrastructure and will cause a complete internet and VoIP outage for all fiber customers in Chelan and Douglas County. We anticipate the actual downtime for each customer to be between 15-30 minutes, but we are calling for a longer window in case there are complications.
Date: Tuesday March 24th, 2026
Time: 12:00am – 6:00am
Scope: All Chelan and Douglas County fiber internet customers will lose their internet and VoIP services for 15-30 minutes sometime during the maintenance window. All services should be restored by 6am.
Chelan PUD Emergency Maintenance
TITLE: Windstorm Damage
LOCATION: Manson
START TIME: 3/12/2026 : 10:00 PM
END TIME: 3/13/2026 : TBD
Purpose: This outage is due to storm damage. Once electrical crews have finished their work, then our fiber crews will be able to start making repairs. Fiber repair will start this evening and will conclude tomorrow.
CCPUD NETWORKS MAINTENANCE NOTICE
TITLE: Red Apple Rd Road Work
LOCATION: Saddlerock
START TIME: 3/5/2026 11:00 PM
END TIME: 3/6/2026 6:00 AM
Purpose: Road Widening work on Red Apple Rd is forcing us to relocate fiber feeding FDT-082.
The Public Utility District No. 1 of Okanogan County will be performing service affecting maintenance on fiber in Omak beginning Wednesday, March 4, 2026 at 2359 and concluding Thursday, March 5, 2026 by 0500.
Location of Work: Columbia St & 3rd Ave E, Omak
Date of Work: March 4-5, 2026
Est. Outage Duration: 2359-0500
Scope of Work: Fiber replacement and splicing
START TIME: 2/09/2026 5:00 PM
END TIME: 2/10/2026 7:00 AM
Previous
Feb 2026 to Apr 2026
Next